228th Ave SE – SE 32nd to Issaquah-Pine Lake Road Intersection Improvements

Subscribe to project updates.

Project Summary

This project will improve the intersection of 228th Avenue SE at Issaquah-Pine Lake Road. The eastbound and westbound left turn pockets will be extended, and the southbound bus-only exiting lane will be re-designed as a regular exiting lane from the intersection. These changes were recommended in the 228th Avenue SE Corridor Study Traffic Analysis Report, which found that the peak AM delay could be improved with specific changes. The report is linked below.



Schedule

March 15, 2016 - Design contract awarded to David Evans and Associates.
Construction Advertisement  - November 2016    

Budget     

$920,000

Resources

News releases

No articles found

Staff Contact

Jed Ireland, Senior Project Engineer, (425) 295-0563