Summary



Join us October 19th – Open House #3 for the Sahalee Way Widening Project.

 

The City of Sammamish is hosting a third open house for the Sahalee Way Widening project, NE 25th Way to NE 37th Way. Please join us for a brief presentation sharing how your feedback has shaped the scope of the project. There will also be an update on what is being done to address broader concerns of traffic, safety, and reducing impacts to trees and property.

 

Meeting Details:

Wednesday, October 19

6-7:30 p.m. (Presentation at the beginning of the meeting)

Boys and Girls Club, Sammamish

825 228th Ave NE, Sammamish, WA 98074

 

Based on feedback and a preliminary design analysis, the recommended scope is for a 3-lane street section with sidewalk and bike lane on the west side, widened shoulder on the east, a raised center median island, and a new traffic signal at NE 28th Place / 223rd Ave NE.  A 5-lane section was analyzed for the corridor, but was found to not improve travel times to Redmond. The City is working on strategies to improve traffic, including expanding the adaptive traffic signal control north to SR 202, in partnership with WSDOT and King County.

 

Alternatives Analysis Report Overview
The City has completed a preliminary design analysis evaluating elements needed to accommodate existing and future traffic. Specifically, the analysis looked at peak travel forecasts for the year 2035 and recommended a 3-lane street section, as well as signal control for NE 28th Place/223rd Avenue NE. The signalized intersection with Hwy 202 was also evaluated for potential improvements.

Sahalee Way Aerial Plot
Sahalee Draft Layout 1 of 3
Sahalee Draft Layout 2 of 3
Sahalee Draft Layout 3 of 3
Alternatives Analysis Report
Alternatives Analysis Appendices

Project Updates

September 27, 2016 - A third Open House is scheduled for Wednesday, October 19th from 6-7:30 PM at the Boys and Girls Club located 825 228th Avenue NE. The presentation will focus on the proposed project scope in response to public comments received. Final engineering design is planned for 2017, and additional open houses will be scheduled share 30% and 60% detail plan levels.

Seeking your feedback - The alternatives analysis report is posted above, and we would like your feedback. If you haven't done so already, please review the questionnaire below, and either mail, email, or call with your questions and comments. You may also follow the "Comment" tab above. Thank you!

Goals and Benefits

The Sahalee Way corridor is vitally important to residents as a major route for entering and existing the Sammamish Plateau. The goal is to design complete street improvements that will accommodate planned growth and maintain the City's character.

Timeline

Request for Qualifications - October 14, 2014
First Open House - June 24, 2015

Second Open House - November 4, 2015, 7-8:00 PM at Boys and Girls Club Teen Center
Third Open House - Wednesday, October 19, 2016, 6-7:30 PM at the Boys and Girls Club

Budget

Construction: $16.9 million planning level estimate for 3-lane configuration.

Public Involvement


Third Open House - October 19, 2016, 6-7:30 PM at Boys and Girls Club
Sahalee Way Comment Form 2016.10.19.pdf
Slide Show_Open House #3.pdf

Questionnaires and Comments Received through 11/20/2015 are below. Still accepting comments - comment form above.

First Open House Comments Part 1.pdf
First Open House Comments Part 2.pdf

Second Open House Comments Part 1.pdf
Second Open House Comments Part 2.pdf
Second Open House Comments Part 3.pdf

Permits, Environmental Review

Coming Soon.

Resources

News releases

Request for Qualifications - Sahalee Way NE Roadway Improvements October 14, 2014
The City of Sammamish Department of Public Works is seeking Requests for Qualifications and Proposed Approach (RFQPA) from qualified civil and multi-modal transportation planning and design firms/teams to provide conceptual d...
 

Staff Contact

Jed Ireland, Senior Project Engineer, (425) 295-0563